Hollow-core floor slabs installation


Hollow-core floor slabs installation



Installation operation start from storage area in the factory and end by placing the hollow-core floor slab on building beams at the site.

THE READINESS OF THE SITE

Beams to be cast on the integrity of the well and the one where the uneven surface does not allow the balance of concrete slabs.
– THE PRESENCE OF CRANE FOR INSTALLATION .
– THE PRESENCE OF THREE WORKERS AT LEAST , ONE WORKER ON THE TRUCK AND TWO WORKERS TO INSTALL THE PANELS ON THE ROOFS .

04

LOADING TO THE SITE

It is lifted concrete slabs to the sites of storage area using a forklift truck five tons and above.

IMG_4625

20140502_144446

INSTALLATION

Hollow core slabs are installed on the beams where based on the distance of 10cm from each beam and so ON untill all the slabs are placed on the whole space required .

DSC_0045

DSC_0022

DSC_0296

once the installation is completed a 5 cm screed concrete is poured above the slabs.unnamed